May 2007 Photo's of RailRoad Progress
|
May 12th, the day began with putting in a gravel floor for work area. |
| Then began the roadbed prep. First the route was cut to 4" below grade level. All site prep is sponsored by Scott's Tractor Service. |
 |
 |
After initial grade cut was made, 4 " of base material was spread and leveled. |
| Working ahead of the grade work, a laser transit is used to monitor the grade change to maintain maximum of 1.5% grade. |
 |
 |
Base material, shown being layed in here, is recycled concrete. All base material and ballast is sponsored by P.A.W. Materials of Odessa, Florida.
www.pawcompanies.com
|
| CP&G members assisted in moving of 6 truck loads of base material, previously delivered, using Scott's equipment. |
 |
 |
As the laying of material progressed down the mainline, base material was loaded onto small trailer that could utilize walking trails to transport it. |
| Base material is dumped onto roadbed close to area it will be laid. |
 |
The two photo's below show a section base prepped then with base material installed.
 |
May 16th, preliminary clearing of the "Y" at Trilby Junction and the departure/arrival track from main yard to Lacoochee. |
| This photo shows where the track will cross one of the walking paths in the park. This section will connect the mainline from Lacoochee to yard and form a reverse loop. |
|
 |
In larger photo the flags that mark the planned route can be seen. Within the next few weeks these areas will be further cleared, grade cut and base applied. |
These photo's show a cut that supplied material for an adjacent fill area to change a 3% grade found to an acceptable level.




This page copyright ©2006-2007, Central Pasco & Gulf Railroad, Inc.All rights reserved.