 |
August 11th, began with installation of rail joiners to the 150 feet of track laid out last week. |
After the joiners are installed the track was given initial alignment then conduits for signal wiring and water were laid along side. |
 |
 |
Next came the ballast. Transferred from a trailer to ballast cars the ballast was then distributed along the right of way. |
This photo shows a stretch of track with ballast installed. Next week final alignment and leveling of this stretch will be done. |
 |
 |
We also laid out another 150 feet or so of track to continue the process next week. |
This photo shows progress of the Dade City Station, donated by Synovus Bank. This is the front view of the station as visitors would approach it. |
 |
 |
This view of the station is from the perspective of a train approaching the station. The portion on the right of this view would be the ticket office and waiting area. The left side the track platform with three tracks. |